Project Qualification report
Assessment of Packhouse, Western Cape for environmental assets
| Report reference | PQ-2611-B19B |
|---|---|
| Version | 1.0 |
| Date prepared | 16 Nov 2026 |
| Rules version | As at 10 Nov 2026 |
| Packhouse, Western Cape | |
| Readiness | A: Ready to start5 of 5 |
| Prepared by | Enerlink |
1.Summary
Enerlink's grouped project: being assessed (not confirmed)
Your plant started in the current monitoring period (MP2), but it is larger than 100 kWp, the size the project admits today.
- Best route
- Being assessed (not confirmed)
Carbon credits through Enerlink's grouped project
Enerlink's grouped project for South African solar, under Verra's Verified Carbon Standard. Registration is pending. It takes systems up to 100 kWp; larger ones are being assessed. Read more from Verra's Verified Carbon Standard - Date that matters most
- 31 Jan 2027: MP2 ends (to be confirmed)
- Next step
- Start onboarding with Enerlink
- Readiness
- A: Ready to start5 of 5
- Met: A route is open or being assessed
- Met: Ownership and carbon rights are clear
- Met: Not already claimed, and attributes not sold
- Met: Generation data is available
- Met: The first-generation date is known
- Estimated reductions
- About 1,400 to 1,700 tCO2e a year (estimate)
2.The plant
What you told us.
Table 1. The plant, as you described it
| Owner | Business, site owner |
|---|---|
| Country | South Africa |
| Capacity | 1.2 MW |
| First generation | Feb 2026 |
| Export share | Not grid connected |
| Monitoring | Full history available |
3.Assessment by route
Each route to environmental assets, best first.
Figure 1. Why this route
Export share
Not grid connected
Half or less: captive
Enerlink's grouped project
Enerlink's grouped project for South African solar, under Verra's Verified Carbon Standard. Registration is pending. It takes systems up to 100 kWp; larger ones are being assessed. Read more from Verra's Verified Carbon StandardBeing assessed (not confirmed)
A new grouped project
A new grouped project under Verra's Verified Carbon Standard, for plants that use most of their own power and that the existing project can't take. Possible if we open it. Read more from Verra's Verified Carbon StandardMay be possible
More than half: grid-connected
Grid-connected project
A carbon project under Verra's VMR0017 method, for plants that export more than half their power. Possible if we open it. Read more from Verra's Verified Carbon StandardNot available
Either way
Certificates
Renewable energy certificates: one for each megawatt-hour generated. Being set up, not available yet. A certificate can't be claimed on the same megawatt-hour as a carbon credit. Read more from the I-REC Standard (I-TRACK)Not available yet
DERs
DERs under the Earth Standard: for reporting your solar's impact, not for sale. Decarb issues DERs from metered generation. Read more from DecarbOpen
Table 2. Routes and status, best first
| Route | Status | What it means for this plant | Condition or next action |
|---|---|---|---|
Carbon credits through Enerlink's grouped projectEnerlink's grouped project for South African solar, under Verra's Verified Carbon Standard. Registration is pending. It takes systems up to 100 kWp; larger ones are being assessed. Read more from Verra's Verified Carbon Standard | Being assessed (not confirmed) | Over 100 kWp: decision by mid-January 2027 (estimate). | Wait for the decision |
Carbon credits through a new grouped projectA new grouped project under Verra's Verified Carbon Standard, for plants that use most of their own power and that the existing project can't take. Possible if we open it. Read more from Verra's Verified Carbon Standard | May be possible | To join, register by 1 Feb 2028. | Register by 1 Feb 2028 |
DERs under the Earth StandardDERs under the Earth Standard: for reporting your solar's impact, not for sale. Decarb issues DERs from metered generation. Read more from Decarb | Open | For reporting your solar's impact, not for sale. | Ask us about reporting |
Renewable energy certificatesRenewable energy certificates: one for each megawatt-hour generated. Being set up, not available yet. A certificate can't be claimed on the same megawatt-hour as a carbon credit. Read more from the I-REC Standard (I-TRACK) | Not available yet | Being set up. | When it is set up |
Carbon credits for grid-connected plantsA carbon project under Verra's VMR0017 method, for plants that export more than half their power. Possible if we open it. Read more from Verra's Verified Carbon Standard | Not available | Exports half or less: a captive plant. | None |
Carbon credits through Enerlink's grouped project
Enerlink's grouped project for South African solar, under Verra's Verified Carbon Standard. Registration is pending. It takes systems up to 100 kWp; larger ones are being assessed. Read more from Verra's Verified Carbon StandardLarger than 100 kWp, so it is being assessed (not confirmed): the project's description must change before it can take this plant. We expect a decision by mid-January 2027 (estimate).
Carbon credits through a new grouped project
A new grouped project under Verra's Verified Carbon Standard, for plants that use most of their own power and that the existing project can't take. Possible if we open it. Read more from Verra's Verified Carbon StandardPossible through a new grouped project. Your plant helps us decide when to open it. To join, this plant must be in its registration request by 1 Feb 2028. We'll confirm the financial check with you.
DERs under the Earth Standard
DERs under the Earth Standard: for reporting your solar's impact, not for sale. Decarb issues DERs from metered generation. Read more from DecarbOpen for plants generating from 2016. DERs from metered generation are for reporting your solar's impact, not for sale.
Renewable energy certificates
Renewable energy certificates: one for each megawatt-hour generated. Being set up, not available yet. A certificate can't be claimed on the same megawatt-hour as a carbon credit. Read more from the I-REC Standard (I-TRACK)Being set up, not available yet. When it is, a certificate can't be claimed on the same MWh as a carbon credit.
4.Key dates
1 Feb 2026 (approximate) Earning begins, inside MP2: Carbon credits through Enerlink's grouped project
31 Jan 2027 (to be confirmed) MP2 ends: Carbon credits through Enerlink's grouped project
31 May 2027 (estimate) Verra approves registration and MP1: Carbon credits through Enerlink's grouped project
1 Jul 2027 (fixed) List before this date to avoid the listing deadline: Carbon credits through a new grouped project
15 Sep 2027 (estimate) MP2 submitted: Carbon credits through Enerlink's grouped project
1 Feb 2028 (approximate) Registration request due: Carbon credits through a new grouped project
● Fixed: set by the rules. ◉ Approximate: built from the month you gave. ○ Estimate: our best forecast. ◌ To be confirmed: waiting on Verra or the project.
5.Information still needed
Settle these and the report gets firmer.
- When your carbon rights started: we assumed from 1 Nov 2025, the project start.
- Exact dates: we used the 1st of the month you gave, so dates that run from them are approximate.
6.Basis and limitations
Assessed against the rules of Verra (VCS), the I-REC Standard, the Earth Standard and Enerlink's projects, as at 10 Nov 2026. Estimated reductions: capacity × typical yield (1,500 kWh per kWp a year) × South Africa's grid factor (0.94 tCO2e per MWh), checked against Enerlink's verified data. Not a forecast of credits.
Guidance only, not advice. Verra and the other standards decide registration and credits; nobody can promise them. Terms.
Terms used in this report
- Grouped project
- One registered carbon project that many plants join over time, so each plant doesn't need its own registration.
- Monitoring period (MP1, MP2)
- A stretch of time over which a project's generation is measured and verified, then credited. A plant joins the period it started in.
- Registration
- Verra's approval of a project. Credits can only be issued once a project is registered.
- Export share
- How much of the plant's generation goes to the grid rather than being used on site.
- Captive plant
- A plant that mainly powers its own site, exporting half or less of what it generates.
- DER
- A Decarb-certified Emission Reduction: one tonne of CO2e cut, issued by Decarb under the Earth Standard. For reporting your solar's impact, not for sale.
- I-REC
- A renewable energy certificate: proof that one megawatt-hour came from a renewable source.